Generally, a provision in a construction contract for private work limiting the contractor’s right to recover additional costs arising from delays outside of the contractor’s control may be enforceable. However, under the Public Bid Law, such a provision has been found to be against public policy. La. R.S. 38:2216 prohibits any public contract provision that purports to waive, release or extinguish the rights of a contractor to recover delay damages if the delay was caused in whole or in part by the acts or omission of the public entity.