Insight

When No Higher Court Remains

Published on: December 10, 2014

On April 20, 2010, BP's Deepwater Horizon rig exploded at a cost of eleven lives. What followed was the largest accidental marine oil spill in history. In the aftermath, BP looked for a solution, ostensibly to cap its exposure and address a swirling PR disaster. BP began to actively negotiate a settlement.

On March 2, 2012, BP agreed to a detailed settlement which set forth specific criteria for recovery under the Fund created by the Agreement. In August of that year, BP asked U.S. District Judge Carl Barbier to approve the settlement. The Agreement was approved.

Despite championing the settlement, BP later filed a lawsuit seeking to set aside the settlement, unless it was interpreted as suggested by BP. BP's challenges were rejected by the Federal District Court. Thereafter, the New Orleans-based Fifth Circuit Court of Appeals affirmed that ruling in a 2-to-1 decision. BP then applied for a Petition of Writ for Certiorari with the United States Supreme Court in a final challenge to the settlement.

About BP's legal maneuvers, Samuel Issacharoff, a New York University Law Professor, said the following: "This case is about a contract that BP signed that it now wishes it hadn't."

One of BP's primary complaints was that, in effect, the settlement could be interpreted to provide recovery for individuals or businesses who could not show a direct link between a financial downturn and the spill. In response, it was stated that the settlement was crafted to use objective measures to gauge whether losses are recoverable.

On December 8, 2014, the U.S. Supreme Court rejected BP's Petition for Writ of Certiorari. As such, the settlement agreement first proposed by BP will remain in place. No higher court remains.

Under the Agreement, potential claimants have 6 months from the Supreme Court's Petition denial to file claims.

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

Make Sure You Are Sure! – A Comment on the Finality of Settlement Agreements under Louisiana Law

Preparing for a trial is a tense and stressful process for attorneys and their clients. Sometimes, during trial preparation, a crucial piece of evidence can come to light that may push a case from a path towards trial to a path towards a settlement agreement. A “settlement” or “compromise” under Louisiana law is just that – an agreement between the parties to settle the dispute raised in the lawsuit, usually with the exchange of a sum of money. Often, settlements are reached in the weeks leading up to trial or even on the courthouse steps.

This type of scenario occurred in Nola Title Company, LLC v. Archon Information Systems. While in the thick of trial preparation, audio recordings from one of the parties were discovered. That party concluded this evidence would be prejudicial to its case at trial, which spurred settlement negotiations. The parties eventually agreed to a compromise and notified the court of the settlement via an email to the judge’s law clerk. The next day, the attorneys reported to court and verbally outlined the terms of the settlement agreement on the official court record.

Two weeks later, the defendants hired new counsel. Two months after that, counsel for the plaintiff forwarded the formal settlement documents to memorialize the agreement that was made between the parties and entered into the court’s record. However, the defendants refused to sign the paperwork and did not timely make the payments that previously were agreed upon. Therefore, the plaintiff filed a motion to enforce the settlement agreement.

In opposition to the motion to enforce, the defendants argued: 1) that their prior counsel did not have authority to enter into the settlement agreement; and 2) that the agreement on the record of the court was invalid because it did not include a provision about the audio recording, which the defendant claimed was a key element of the agreement between the parties. After an evidentiary hearing, the trial court found that the settlement that was stated on the record was an enforceable settlement agreement.

The Louisiana Court of Appeals for the Fourth Circuit affirmed the ruling of the trial court. In its opinion, the appellate court includes a summary of the law governing settlements in Louisiana. After a thorough review of the applicable law, the court came to the following conclusions:

  • The settlement agreement on the record of the court was a binding settlement agreement, even if the parties contemplated a future formal written agreement;
  • When a compromise is placed on the record, the recital must include full disclosure of the material terms;
  • Any “missing terms” from the recorded settlement agreement were not a material element of the settlement; and
  • The defendants’ prior counsel had authority to enter into the settlement as written.

Based upon the court’s ruling, if the parties have a meeting of the minds and settlement terms are entered on the trial court record, there are no “do-overs” or “take-backs.” It is important to “make sure you are sure” when entering the crucial courthouse steps settlement agreement.

References:

Nola Title Company, LLC v. Archon Information Systems, et. al., 2022-CA-0967 (La. App. 4 Cir. 4/13/23), 360 So. 3d 166.

Insight

Arbitration Awards: U.S. Fifth Circuit Confirms Judicial Deference

Arbitration is a favored method of dispute resolution in the energy and construction sectors, where complex, high-value contracts often generate multimillion-dollar disputes. Understanding the courts' standard of review of arbitration awards directly impacts risk assessment, contract drafting, and dispute resolution strategies. A recent U.S. Fifth Circuit decision reinforces the limited grounds for judicial intervention, a principle that remains central to the effectiveness of arbitration as an efficient alternative to litigation.

In United States Trinity Services, LLC v. Southeast Directional Drilling, LLC, a drilling subcontractor obtained a $1.7 million arbitration award against the general contractor for standby costs incurred on a pipeline installation project. The subcontractor incurred costs when ordered to stop work for causes outside its control, including delayed permits, mud infiltration, and COVID-19. The subcontract contained a provision that called for reimbursement of standby costs. On appeal, the general contractor sought to vacate the award in the U.S. Northern District of Texas, arguing that the arbitration panel failed to properly interpret various contract provisions related to standby costs and exceeded its authority and acted in manifest disregard of Texas law in interpreting the contract.

The Federal Arbitration Act, 9 USC §10 (“FAA”) applies and provides the exclusive grounds to vacate an award: corruption, fraud, evident partiality, misconduct in refusing to postpone the hearing, refusing to hear evidence, or where arbitrators exceeded their powers. The U. S. Fifth Circuit Court of Appeals noted that the FAA was enacted to create a national policy favoring arbitration; the arbitrator’s authority derives from the parties’ contract; and once parties agree to arbitrate, they “bargain for” the arbitrator’s, not the court’s, interpretation of their contract.

The Court instructed that a party challenging an award bears a high burden to show that the arbitrator ignored the contract. It is not sufficient to show the arbitrator erred in interpreting the contract. The question the court asks is “whether the arbitrators construed the contract at all” not “whether they construed it correctly.” A court should not reassess the merits of the arbitrator’s decision. Here, the award recited the pertinent contract terms and the arbitrators’ analysis. This showed the arbitrators considered the contract provisions, thus ending the Court’s inquiry.

The Court rejected the argument that the arbitrators manifestly disregarded the law in interpreting the contract. “Manifest disregard” – a judicially-created concept – is not a freestanding ground for vacatur. It does not serve as a separate basis to establish that arbitrators exceeded their powers. Otherwise, the FAA’s stated grounds for vacatur would be expanded to essentially a “full-bore” judicial review process.*

However, the Circuits are split on the validity of manifest disregard of the law or contract as a basis to vacate an award. See for example, Dewan v. Walia, where the U.S. Fourth Circuit Court of Appeals vacated an award after finding the arbitrator’s contract interpretation ‘untenable.”

Mary Anne Wolf, PE, FCIArb, is an arbitrator, mediator, and attorney in construction, energy, commercial and complex cases.

References:

United States Trinity Services, LLC v. Southeast Directional Drilling, LLC, 2025 WL 1218096 (5th Cir. 2025).

Dewan v. Walia, 544 Fed Appx 240 (4th Cir. 2013).

* Hall Street Assoc., LLC v. Mattel, 128 S.Ct. 1396 (2008).

Insight

Louisiana Supreme Court issued a significant ruling in a class action case involving tax credits for solar panels

Recently, the Louisiana Supreme Court issued a significant ruling in a class action case handled by Keogh Cox partners Chris Jones and Nancy Gilbert. The case involved tax credits for solar panels. The Court’s ruling overturned a lower court decision that held an Act of the Legislature unconstitutional. After the plaintiffs’ Application for Rehearing was denied, the Court’s decision is now final.

In Ulrich, et al. v. Kimberly Robinson, Secretary of the Louisiana Department of Revenue, 2018-0534 (La. 3/26/19), 2019 WL 1395316, the class action plaintiffs were persons who purchased and installed residential solar panel systems in their homes. When they claimed the solar electric system tax credits on their 2015 state tax returns pursuant to La. R.S. 47:6030, the tax credits were denied by the Louisiana Department of Revenue, based on Act 131 of the 2015 legislative session. Act 131 capped the maximum amount of solar panel tax credits to be granted by the Department of Revenue, and the plaintiffs’ claims were made after the cap was exhausted.

When their claims for the tax credits were denied, plaintiffs filed a declaratory judgment action seeking to declare Act 131 unconstitutional. During the pendency of the suit in the district court, the Louisiana Legislature enacted Act 413 which provided additional funding for solar tax credits. Under Act 131, all taxpayers whose solar panel tax credit claims were previously denied would receive the entirety of their tax credits over installments. The district court declared Act 131 unconstitutional and concluded that Act 413 did not moot the controversy.

Because the district court declared Act 131 unconstitutional, the Department directly appealed the decision to the Louisiana Supreme Court. Oral arguments occurred in October of 2018. In the Court’s recent opinion, it concluded that Act 413 mooted the controversy. According to the Court, the plaintiffs no longer maintained a “justiciable controversy” because Act 413 provided for the payment of the entirety of the previously denied tax credits. Accordingly, the Court overruled the district court’s judgment that declared Act 131 unconstitutional. Plaintiffs filed an Application for Rehearing and that request was recently denied, making this decision final.

Chris Jones is a partner with Keogh Cox in Baton Rouge, LA. He focuses his practice on class actions and mass torts, and handles these matters in courts throughout the country. He is a life-long resident of Baton Rouge, where he lives with his wife and four children.

Christopher K. Jones

Partner
B.P.
Class Actions
Energy
Federal Courts
Gulf Oil Spill
Oil & Gas
Supreme Court