Insight

Fourth Circuit Brings Clarity to Peremption Statute in Suit Against Design Professional

Published on: February 15, 2016

The question addressed in MR Pittman Group, LLC versus Plaquemines Parish Government, 2015-0396 (La.App. 4 Cir. 12/2/15) was whether the five-year peremptive period set by La. R.S. 9:5607 displaces Louisiana’s general one-year prescriptive period set by La. C.C. art. 3492, when applied to tort claims against design professionals. Finding a contractor’s claim against the project engineers prescribed, the MR Pittman court held that the one-year prescriptive period governs tort claims against design professionals.

La. R.S. 9:5607 explicitly provides a peremptive period that extinguishes all claims against architects, engineers and other design professionals five years after the project is completed, thus limiting design professional liability associated with the project. The MR Pittman plaintiff/contractor argued that the statute also eliminates the one-year prescriptive period and instead creates a special five-year prescriptive period, which allowed the contractor up to five years to bring its claim against the engineers to recover for delay and other extra costs allegedly resulting from deficiencies in the construction plans. This interpretation effectively expands tort liability by increasing the time period for bringing a tort claim from one to five years. In rejecting this argument, the MR Pittman court clarified that under the statute any claimant has no more than five years after project completion to bring suit against the design professional for any cause. However, a tort claimant still has only one year to file suit from the date he “knew or should have known” of damage caused by the alleged wrongful actions of the design professional.

A secondary question addressed in MR Pittman was the date of commencement of the one-year prescriptive period, which under La. C.C. 3492 commences to run from the day damage is sustained. The defendant/engineers argued that prescription commenced when the contractor first became aware of the alleged design deficiencies early in construction, as evidenced by the contractor’s notice to the owner of the deficiencies. The contractor argued that it could not fully appreciate its damages until the change orders were resolved later in the project. Citing Louisiana Supreme Court precedent holding that the quantum of damages need not be certain or fully incurred to trigger commencement of prescription, Harvey v. Dixie Graphics, Inc., 593 So.2d 351, 354 (La. 1992), the court agreed with the engineers’ position and dismissed the claims.

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

Fourth Circuit Brings Clarity to Peremption Statute in Suit Against Design Professional

The question addressed in MR Pittman Group, LLC versus Plaquemines Parish Government, 2015-0396 (La.App. 4 Cir. 12/2/15) was whether the five-year peremptive period set by La. R.S. 9:5607 displaces Louisiana’s general one-year prescriptive period set by La. C.C. art. 3492, when applied to tort claims against design professionals. Finding a contractor’s claim against the project engineers prescribed, the MR Pittman court held that the one-year prescriptive period governs tort claims against design professionals.

La. R.S. 9:5607 explicitly provides a peremptive period that extinguishes all claims against architects, engineers and other design professionals five years after the project is completed, thus limiting design professional liability associated with the project. The MR Pittman plaintiff/contractor argued that the statute also eliminates the one-year prescriptive period and instead creates a special five-year prescriptive period, which allowed the contractor up to five years to bring its claim against the engineers to recover for delay and other extra costs allegedly resulting from deficiencies in the construction plans. This interpretation effectively expands tort liability by increasing the time period for bringing a tort claim from one to five years. In rejecting this argument, the MR Pittman court clarified that under the statute any claimant has no more than five years after project completion to bring suit against the design professional for any cause. However, a tort claimant still has only one year to file suit from the date he “knew or should have known” of damage caused by the alleged wrongful actions of the design professional.

A secondary question addressed in MR Pittman was the date of commencement of the one-year prescriptive period, which under La. C.C. 3492 commences to run from the day damage is sustained. The defendant/engineers argued that prescription commenced when the contractor first became aware of the alleged design deficiencies early in construction, as evidenced by the contractor’s notice to the owner of the deficiencies. The contractor argued that it could not fully appreciate its damages until the change orders were resolved later in the project. Citing Louisiana Supreme Court precedent holding that the quantum of damages need not be certain or fully incurred to trigger commencement of prescription, Harvey v. Dixie Graphics, Inc., 593 So.2d 351, 354 (La. 1992), the court agreed with the engineers’ position and dismissed the claims.

Insight

“Collectibility” in Legal Malpractice: Can a client have greater rights against an attorney that existed in the underlying case?

It is well-established that a client in legal malpractice shall have no greater rights against their attorney than they had against the original defendant. That is, until the recent decision by the Supreme Court in Ewing v. Westport Insurance Corporation, 20-00339 (LA. 11/19/20), 2020 WL 6789490 where the Louisiana Supreme Court held that the “collectibility“ of the underlying judgment against the defendant is neither part of the plaintiff’s burden of proof nor the proper subject of an affirmative defense.

In Ewing, the defendant/attorney fax-filed a petition for damages but failed to forward the original petition within seven days as required by statute. As a result, the claim he sought to advance on behalf of Elaine Ewing prescribed. Ewing sued her attorney and his insurer.

Prior to trial, the tortfeasor testified that he would have filed for bankruptcy had an excess judgment been entered. On this basis, the defendants obtained a motion for summary judgment establishing that the underlying tortfeasor would have been unable to pay any amount above the $30,000 in available insurance coverage. Following trial, an award of $30,000 was entered in favor of the plaintiff and the plaintiff appealed.

The appellate court reversed citing to the decision in Rodriguez v. Traylor, 468 So.2d 1186, 1188 (La. 1985) which held that “the wealth or poverty of a party to a lawsuit is not a proper consideration in the determination of compensatory damages.“

The Supreme Court upheld the appellate opinion. In the analysis, Chief Justice Johnson on behalf of the majority also cited to the Rodriguez decision for the proposition that the wealth of the tortfeasor is not relevant to damages. The majority acknowledged that a majority of courts nationwide hold that the collectibility of a judgment is an essential element of a plaintiff’s legal malpractice case. It also observed “a growing trend” in other states to allow the defendant/attorney to plead collectability as an affirmative defense. Nevertheless, the Supreme Court in Ewing chose to follow neither position.

The defendants in Ewing did not argue that collectibility was part of the plaintiff’s burden. However, they did assert an affirmative defense on this basis. In rejecting this defense, the Ewing court found that nothing in statutory law of Louisiana limits damages based upon the collectibility of a judgment against a particular tortfeasor. In Ewing, it was established that the tortfeasor would have been immediately unable to pay an excess judgment. Nevertheless, the majority highlighted that a money judgment is valid for 10 years and may be revived for successive 10-year periods. As such, the court concluded that the money judgment has intrinsic value, regardless of immediate collectibility. To quote the majority, “impecunity is a snapshot in time.”

The concurring opinion by Justice Weimer reasons that there may be certain and rare cases where the underlying tortfeasor is truly judgment proof. In that circumstance, he writes that summary judgment in favor of the defendant may be appropriate but not under the record before the court.

Writing for the dissent, Justice Crain observed: “Thirty states have determined collectibility is relevant in a legal malpractice action. No state has reached a contrary conclusion, until now.” According to the majority, the absence of any statute making collectability a relevant consideration mandated the result under our civilian traditions. Justice Crain disagreed and argued that the majority opinion is inconsistent with the Code of Evidence articles which generally allow the admissibility of relevant evidence such as an inability to pay. La. L.C.E. art. 402. In support of his position, Justice Crain gave a hypothetical scenario involving an insolvent, uninsured driver who rear-ends a world-class professional athlete rendering him a paraplegic, resulting in damages and $50 million. About this hypothetical, he states:

“What did the plaintiff lose, or what harm did the lawyer cause the plaintiff, when the lawyer failed to preserve the claim against the insolvent, uninsured driver? The lawyer did not cause the paraplegia, nor did he caused a loss of $50 million, as that money was clearly uncollectible.“

To Justice Crain, the determinative question is the value of the lost judgment.

Insofar as the majority and concurring opinions highlight the absence of any statutes to support their conclusions, it would not be surprising for this issue to be considered by the legislature in coming years.

Collin is a Keogh Cox partner who litigates injury, commercial, and legal malpractice disputes. He lives in nearby Zachary, Louisiana with his wife Melissa and three all too active children. He is an outdoorsman, a tennis player, a cook, and a hobbyist writer.

This blog was written in partnership with Andrew "Drew" Blanchfield whose practice also includes professional liability defense.

Insight

Court Finds Legal Malpractice Claim Perempted Because the Client Knew It Received “Bad Advice” More than One Year Before Suit Was Filed

Legal malpractice claims in Louisiana are governed by a peremption period that cannot be interrupted or suspended. La. R.S. 9:5605(A) provides that a legal malpractice claim must be brought one year from the date of the alleged malpractice, or within one year from the date the alleged malpractice should have been discovered. However, even when a claim is filed within one year of discovery, it must be filed within three years of the date of the alleged malpractice. If a party fails to assert a legal malpractice claim before the peremption period expires, the right to bring the claim is lost.

The Louisiana Supreme Court holds that “peremption commences to run in a legal malpractice case when a claimant knew or should have known of the existence of facts that would have enabled him to state a cause of action for legal malpractice.” In Crosby v. Waits, Emmett, Popp & Teich, LLC, the court recently examined the types of circumstances that should inform a plaintiff that an act of alleged malpractice occurred, which would trigger the peremptive period in which the plaintiff’s claim must be filed.

The plaintiff in Crosby owned 75% of a company and was in the process of buying out the minority stakeholder. The company was involved in litigation at the time. Initially, the minority stakeholder maintained all of the recovery and risk related to the suit. In April 2016, an attorney advised the plaintiff to accept an offer to split the recovery and risk in the suit 50/50 as part of the sale. The plaintiff then accepted the 50/50 offer. The litigation concluded after the sale, in February 2018, and resulted in an adverse judgment for which the plaintiff was responsible pursuant to the 50/50 agreement.

The plaintiff filed suit on February 12, 2019, within one year of the verdict in the underlying litigation, and claimed that its attorney committed malpractice when he advised that plaintiff accept the offer to split the recovery and risk in the suit. Specifically, it was alleged the attorney failed to examine the nature of the litigation or discover that the seller’s employees were aware the suit bore serious risk. The plaintiff’s representative testified that he did not keep track of the litigation and therefore could not have known the attorney engaged in the alleged malpractice until the jury rendered its verdict in the underlying suit.

However, the minority stakeholder testified that he knew the 50/50 offer was a bad deal for the plaintiff. Another employee testified he thought the risk of loss in the underlying suit was apparent to everyone involved. The court agreed. Based upon the evidence presented, “it should have been obvious to all concerned that the 50/50 option was favorable” to the minority stakeholder, who was adverse to the plaintiff’s interest.

The court held that the plaintiff should have known its attorney may have committed an act of malpractice when he advised it to accept the 50/50 split before the underlying litigation concluded. Accordingly, suit was not filed within one year of when the plaintiff should have known the alleged act of malpractice occurred. The plaintiff’s claims that it lacked such knowledge could not stand up to conflicting evidence. Thus, the claim was peremepted, and the plaintiff’s suit was dismissed.

Case References:

Crosby v. Waits, Emmett, Popp & Teich, LLC, 2022-0395 (La. App. 4 Cir. 11/21/22), 352 So. 3d 145.

Jenkins v. Starns, 2011-1170, p. 15 (La. 1/24/12), 85 So.3d 612, 621.

No items found.
Architects
Construction
Contractors
Engineers
Peremption
Prescription
Professional Liability