A Matter of Control: Vicarious Liability in Construction Projects

Published on: May 16, 2023

Under Louisiana’s comparative fault system, each party in a lawsuit generally is only liable for their own percentage of fault. However, in some instances, a party may be “vicariously” liable for the fault of another party. One example of vicarious liability is an employment relationship, where an employer can be liable for the fault of its employees. On the other hand, vicarious liability generally does not apply when the alleged “employee” is found to be an independent contractor. Whether a worker qualifies as an employee or an independent contractor often becomes an important issue in suits related to construction projects.

The test for determining whether a party is an employee or an independent contractor involves analysis of who has the right to control his or her work. In the construction context, courts distinguish between “operational control” (which suggests an employment relationship) and control as it relates to the results of the work (which suggests an independent contractor relationship). Two recent cases examine this issue and provide examples of how courts analyze the type of control necessary to establish vicarious liability in the construction projects.

In Stonetrust Com. Ins. Co. v. TBT Contracting, Inc. of LA, homeowners hired a general contractor to renovate their home. During the project, an electrical subcontractor was injured after falling through an attic space. It was alleged that the general contractor created a hazard by cutting a hole in the attic and concealing it. The plaintiff sued the general contractor and the homeowner. The court had to determine whether the homeowner could be liable for the subcontractor’s injuries, which would require a finding that the homeowner was vicariously liable for the general contractor’s fault.

The plaintiff argued that the homeowners were particularly involved in the project. It presented evidence to show the homeowners would give suggestions regarding the work to be performed and also directed alterations or additions to the work. The plaintiff argued that this demonstrated control over the general contractor’s work. However, the court disagreed. Despite the homeowners’ level of involvement, the court held that their control was limited to the results of the work, and was not “operational control.” The general contractor therefore was an independent contractor, and the homeowners were not vicariously liable for its acts.

In Baham v. Fisk Elec. Co., a city worker brought suit against a general contractor after suffering injuries from an electrical shock. The worker alleged that the general contractor was vicariously liable for the fault of its subcontractor. While evidence showed the subcontractor relied on the general contractor for the location of its work, the court found that this was not “operational control.” The court observed that general contractors are entitled to exercise supervisory control over its independent contractors to ensure compliance with the contract. It further found that suggestions or instructions given to an independent contractor do not equate to control over the methods or details of the work. Absent such “operational control” vicarious liability could not be imposed.

Though they may be limited to their facts, these cases show courts usually require a showing of more than suggestions or instructions regarding the work to establish the “operational control” necessary to trigger vicarious liability. Absent such a showing, independent contractors usually remain independent.

Case References:

Stonetrust Com. Ins. Co. v. TBT Contracting, Inc. of LA, 2022-0971 (La. App. 1 Cir. 4/14/23), 2023 WL 2947826

Baham v. Fisk Elec. Co., 2022-0551 (La. App. 4 Cir. 3/22/23), 2023 WL 2595253

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

Black Boxes: The Secrets Your Vehicle Keeps

By Brian Butler

Many do not realize modern vehicles are always ready to record critical driving information. As with airplanes, most passenger vehicles are now equipped with Event Data Recorders (EDR), or "Black Boxes." This information may be critical after an accident to show what happened, and who was at fault.

EDRs may record pre-event data for five seconds before and one second after an accident, possibly including vehicle speed, engine speed, percent throttle, change in velocity, and whether the brakes were applied. The make and model of the vehicle will determine what data is available. If you want this data, you must act quickly because it will be “overwritten” at some point if the vehicle continues in use.

It is also important to retain a competent expert to download the data. In Laborde v. Shelter Mutual Insurance Co., 82 So. 3rd 1237 (La. 3/9/2011), the trial court excluded the printout of data downloaded from a Black Box because of the boxes "chain of custody" and the method the information downloaded. It is important that your legal team knows how to obtain and preserve this evidence.

Data from Black Boxes can be useful in many ways. In some cases, it may help to prove that the accident involved a low impact or to show that no brakes were applied. In other cases, it may harm your position, but the data is almost always relevant. There are costs in downloading and interpreting the data. But in the right case, the secrets kept in the Black Box may be the only way to reveal the truth.

Brian has been doing defense work for the last 28 years. He has handled all types of defense matters over his career, but in recent years his practice has been focused in serious injury or damage cases and has worked extensively with experts involving complex cases, fire cases, and forensic work.

Insight

When It Comes to Real Estate, Get It In Writing

As the old adage goes, it’s always safest to get an agreement in writing. In Louisiana, when an agreement is about the sale of real estate, the adage is law. A contract for sale must be in writing as provided in Louisiana Civil Code articles 1839 and 2440.

This long-standing rule was at issue in the recent case of Holmes v. Paul, 19-130 (La. App. 5 Cir. 10/2/19), 279 So. 3d 1068. In Holmes, the plaintiff/seller and defendants/purchasers entered into a purchase agreement for a Metairie home which required a closing by no later than April 29, 2016. The contract was a standard form Louisiana purchase agreement which required that any change in the closing deadline be written and signed by both parties. The parties later entered a written extension of the closing deadline to May 6, 2016.

Three days before the closing, the home appraised for $14,000 below the purchase price, leading the seller’s agent to encourage the purchasers’ agent to pursue an appraisal review. However, the parties did not sign a written extension of the May 6, 2016 closing deadline. Thereafter, the seller agreed to decrease the purchase price to the appraised value, but on the same day the purchasers sent a signed cancellation. The seller sued the purchasers for breach of contract, arguing that the parties verbally agreed to extend the closing deadline and intended to execute a written extension as soon as they determined a feasible closing date.

The purchasers moved for summary judgment on the ground that the purchase agreement had expired and was unenforceable. The Court agreed. The purchase agreement expressly required that extensions be made in writing signed by both parties. Upon the expiration of the May 6, 2016 closing deadline, the contract was unenforceable.

The seller also asserted a detrimental reliance claim, arguing she was lulled into not insisting on a written extension because the purchasers’ agent agreed to it orally. However, the seller conceded her awareness that an extension had to be in writing. As such, her reliance was not reasonable. The court further noted the absence of evidence that the purchasers themselves agreed to orally extend the contract or to waive the writing requirement.

Unfortunately, business deals in the modern world cannot be finalized by a handshake. Remember that when you buy and sell property in Louisiana -- get it in writing.

Marty Golden has been practicing law based in Baton Rouge, Louisiana for over thirty years, concentrating in civil litigation primarily involving injuries, property damage, insurance coverage, and contract disputes. Much of his practice is defending and advising real estate agents in suits by property buyers and sellers, but Marty also defends other professionals, insurance companies, manufacturers, and business owners. Marty has a special interest in all things procedural, because they are the rules of the road for litigators and knowing them better than his opponent gives him a leg up in court.

Insight

Employment Law - New Statute Changes the Rules on Hiring

Effective August 1, 2021, La. R.S. 23:291.2 will impact the hiring practices used by many employers. Under the new statute, unless otherwise allowed by law, “when making a hiring decision, an employer shall not request or consider an arrest record or charge that did not result in a conviction, if such information is received in the course of a background check.” This is a dramatic change for employers who consider arrest histories in the hiring process. But the statute does not stop with arrest records.

When considering “other” types of criminal history records, i.e., convictions or pleas, an employer “shall make an individual assessment of whether an applicant’s criminal history record has a direct and adverse relationship with the specific duties of the job that may justify denying the applicant the position.” In this assessment, the employer is to consider:

(1) The nature and gravity of the offense or conduct;

(2) The time that has elapsed since the offense, conduct, or conviction; and,

(3) The nature of the job sought.

Upon written request, an employer shall also make available to the applicant any background check information used during the hiring process. While an arrest is not proof an applicant engaged in criminal conduct, a conviction record is usually sufficient to show criminal conduct. See EEOC guidance at https://www.eeoc.gov/pre-employment-inquiries-and-arrest-conviction.

With convictions, the new Louisiana statute places a burden on the employer to make an assessment as to whether the criminal offense has a direct relationship to the specific job duties of the applicant. The statute gives little guidance as to how employers are to reach a conclusion.

At its core, the statute prohibits requests for arrests records and requires an employer to conduct an analysis as to whether a conviction is relevant to the job function before refusing to hire an employee on the basis of a conviction. The statute minimizes administrative burdens when it bars a consideration of arrests. Yet, it sets forth three factors employers must now weigh and measure for other criminal records. One reasonably asks how this statute- which appears designed to limit discretion in rejecting applicants with documented criminal records- will impact “negligent hiring” claims and other areas of the law.

Chelsea A. Payne

Partner
Construction
Contractors
Louisiana