Insight

Supreme Court Rules Against Broad Application of Indemnity Provision in Engineer’s Contract

Published on: June 3, 2020

The Supreme Court ruling in Couvillion Group, LLC v. Plaquemines Parish Government, 2020 -00074 (La. 4/27/20) is a reminder that an indemnity claim must be sufficiently related to the principal demand and that contract indemnity provisions are to be strictly construed.

In Couvillion, the general contractor sued the owner of a public works port project for contract delay damages resulting from a cease work order issued to allow redesign of a fuel tank platform. When the contractor submitted its delay claim, the owner requested that its project engineer review it and make recommendations. The engineer recommended payment of a little over $1 million dollars. When the owner refused to pay, the contractor sued. In response, the owner filed a third-party demand against the engineer alleging that its recommendation was erroneous and excessive and that, if it was bound by the engineer’s recommendation, then the engineer must indemnify the owner.

On behalf of the engineer, Keogh Cox attorneys argued that the engineer should not be required to reimburse the owner for any delay costs and asked for dismissal through an exception of no cause of action. Code of Procedure Article 1111 provides that a defendant in a principal action may bring in any person who may be liable to him for all or part of the principal demand. Here, that was not the situation. The engineer was not liable to the owner for any part of the contractor’s delay claim because the engineer did not cause the delay. The delay damages were incurred before the engineer made a recommendation for payment. The events giving rise to the two claims were separate and distinct: the main demand arose from the project delay and the third- party demand arose from the engineer’s recommendation of the claim amount. The Court commented that the principal claim against the owner for delay damages was too attenuated from the owner’s claim against the engineer, thus the third-party demand was improper.

The owner also relied on the indemnity provision in the engineer’s contract that required the engineer to indemnify the owner against any and all claims for personal injury or “damages to property” that may arise from its services. The Court held that the plain meaning of the term did not include the economic-only losses related to the subject delay claim. The Court further reasoned that indemnity agreements are to be strictly construed, rejecting the owner’s broader interpretation.

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

RENTER BEWARE: Hidden Risks in Lease Agreements

With home prices soaring in today’s housing market, many people choose to rent rather than buy. Factored into their decision is the style, the square footage, the location, and other criteria, but few renters consider one risk that comes with many, if not most, leases. Many renters are exposed to personal liability for accidents occurring on the premises, and they don’t even know it.A lease is executed between the renter/tenant (the “lessee”) and the property owner (the “lessor”). By law, the lease imposes general obligations on both parties.The lessee (renter) is bound:

1. to pay the rent in accordance with the agreed terms;

2. to use the thing as a prudent administrator and in accordance with the purpose of which it was leased; and,

3. to return the thing at the end of the lease in a condition that is the same as it was when the thing was delivered to him, except for normal wear and tear. LSA C.C. Art. 2683

The lessor (property owner) is bound:

1. to deliver the thing to the lessee;

2. to maintain the thing in a condition suitable for the purpose of which is was leased; and,

3. to protect the lessee’s peaceful possession for the duration of the lease.” LSA C.C. Art. 2682.

These general obligations are typically expanded by terms in the lease because the lessee and lessor are “free to contract for any object that is lawful, possible and determined or determinable.” Family Care Services, Inc. v. Owens, 46 So.3d 234 (La. App. 2 Cir. 8/11/10). This “freedom of contract” allows the parties to construct their own bargains, shifting certain rights and obligations. In many commercial and residential lease agreements, this shifting includes a transfer of the liability for vices or defects on or in the leased premises.Although the lessor warrants that the leased premises is free of vices or defects, Louisiana law allows the lessee to assume responsibility for the condition of the leased premises under LA. R.S. 9:3221. Often, lessees assume that the lessor, as the owner of the premises, will be responsible if there is an accident. However, cases such as Jamison v. D’Amico, 955 So.2d 161 (La. App. 4th Cir. 3/14/07) demonstrate that the owner may be entirely free of fault even though they owned a defective premises which caused an accident. In Jamison, a worker was injured when a floor collapsed beneath her. There was insufficient evidence that the owner was aware of the defective floor. Because the lease contained a clause shifting responsibility, the owner was under no duty to inspect the premises and was dismissed from the case.A lesson to all renters: read and understand the provisions in your lease. Even if you like the colors and the location, you should also like the lease contract before you sign it.

Insight

To Err is Human, To Rescind-Declined

The Louisiana Supreme Court recently addressed the impact of contractual "errors" in Cynthia Fry Perionnet and Elizabeth Fry Franklin v. Matador Resources Company, 2012-2292, 2012-2377, -- So. 3d --.

The Perionnet case involved a dispute over the intent of a contract to extend a mineral lease. The property owners believed that the lease was extended as to only 168.95 acres of nonproducing land. The defendant/lessors argued that the contract contemplated that the lease would extend to the entire 1850.34 acres to include producing wells. Plaintiffs/property owners argued that their unilateral error regarding the terms of the contract was ground for rescission. The jury ruled in favor of the defendant/lessors. The Court of Appeal reversed. The Supreme Court granted writs.

The Perionnet Court began its opinion with an overview of basic tenets of contract law. The Louisiana Civil Code defines a contract as "an agreement by two or more parties whereby obligations are created, modified, or extinguished." La. C.C. art. 1906. Contracts are formed through offer and acceptance. La. C.C. art. 1927. Once formed, contracts have "the effect of law for the parties and may be dissolved only through the consent of the parties or on grounds provided by law." La. C.C. art. 1983. One such "ground" under Louisiana law is "error." La. C.C. art. 1948.

The Louisiana Civil Code recognizes two forms of error: mutual error (both parties are mistaken) or unilateral error (only one party is mistaken). However, for either error to cause the dissolution of a contract, the error (1) must effect the cause of the obligation and (2) the other party must have known that the matter impacted by the error was the reason for the contract. La. C.C. art. 1949. In a case of mutual error, the court can reform the contract. Either partial or full rescission is the only remedy available for unilateral error. La. CC. art. 1952.

A party challenging a contract for unilateral error must also prove that the error was excusable. "Louisiana jurisprudence is sprinkled with cases which deny relief to the parties who claim an agreement should be invalidated because of unilateral error which is caused, in large part, by the complaining party's inexcusable ignorance, neglect or want of care." Id. p. 25.

The Perionnet Court found that the plaintiffs' alleged mistake was inexcusable. The defendants demonstrated that: 1) plaintiffs could show no excuse for failing to read and understand the contract; 2) plaintiffs' agents who negotiated and reviewed the contract were self-proclaimed experts in oil and gas; and 3) the original lease was on the plaintiffs' agent's own forms. The Court found a "sea of flags" in the written agreement that should have notified the experienced plaintiffs that the agreement extended to the entire property. Therefore, the Court found that the mistake was easily detectable and could have been rectified by a minimal amount of care, i.e. "by simply reading the document and/or requesting simple changes to the written offer before acceptance." Id. at 30.

The Supreme Court's Perionnet decision serves as a healthy reminder of a basic concept - read your contracts. Although to err may be human, it can affect your bottom line.

Insight

Privacy (Or Lack Thereof) in an Increasingly Digital Age

“Historically, privacy was almost implicit, because it was hard to find and gather information. But in the digital world, whether it's digital cameras or satellites or just what you click on, we need to have more explicit rules - not just for governments but for private companies.” -Bill Gates

Supreme Court oral arguments were heard earlier this week in Carpenter v. United States, a closely watched case which stands to impact what privacy means in our digital age. The case will decide whether law enforcement is permitted to gather cellphone data from third-party service providers like Verizon and AT&T without a warrant. Carpenter presents the latest installment in the eternal struggle between the need for safety and the desire to prevent a surveillance state.

In Carpenter, the FBI investigated a series of robberies at Radio Shack and T-Mobile stores in Detroit. Suspecting that Carpenter was operating as a “getaway driver,” the FBI sought and obtained without a warrant the location data for his cell phone. This data revealed that Carpenter (or at least his cell phone) was near the stores at the times of the robberies­­­­­­––damning evidence.

Carpenter argued that the government’s collection of his cell photo data was a “search” under the 4th Amendment, a "search" which would require a warrant supported by “probable cause.” The government maintained that privacy concerns were addressed when law enforcement complied with the Stored Communications Act which allows law enforcement access upon a showing that the information sought is "relevant and material" to an ongoing investigation. The government further argued that there is no reason to afford greater protection to cell phone data than given to other data such as bank records and dialed telephone numbers which can be obtained without a warrant.

The issues presented in Carpenter are not new, but are magnified by the awesome power of advancing technology to track our movement and assembly with others. The Louisiana court in State v. Bone, 12-34 (La. App. 5 Cir. 9/11/12), 107 So. 3d 49, held that an exclusive user of a cell phone did not have a reasonable expectation of privacy to the call detail record log associated with the phone. The court reasoned that access to the information in the detail record log was voluntarily surrendered by the defendant to the phone’s providers. However, in United States v. Jones, 132 S. Ct. 945 (2012), the United States Supreme Court found that the installation of a GPS device on a vehicle to monitor the vehicle’s movement was a “search” under the 4th Amendment. Carpenter addresses the intersection of these two cases.

By carrying a cell phone you know can track your movements, do you lose any reasonable expectation of privacy? Or, would allowing warrantless access to this information be akin to the prohibited GPS search in United States v. Jones? The Supreme Court will soon decide. How it chooses will impact criminal litigation and by extension how cell phone data is regarded in civil suits. More importantly, it may also impact the relationship between citizens and their government.

Collin LeBlanc is a Keogh Cox partner and experienced litigator who concentrates in injury, commercial, and legal malpractice disputes. He lives in nearby Zachary, Louisiana with his wife Melissa and three all-too-active children. He is an outdoorsman, a tennis player, a cook, and a hobbyist writer.

Mary Anne Wolf, PE, FCIArb

Partner
Contracts
Engineers
Supreme Court